Construction Materials Calculator

Enter the covered area to estimate the bricks, cement, steel, sand and crush for the grey structure of a house. Adjust the per-square-foot figures to match your design.

By Bilal Naeem · Methodology · Source: Glorious Builders: construction material calculator and BOQ, Lahore (verified April 2026)

Try:
sq ft
All floors. A 5 Marla double-storey is about 2,250 sq ft.
bricks
bags
kg
cft
cft
%

Estimated grey-structure materials

71,000 Bricks

For 2,250 sq ft covered, including 5% wastage

Bricks70,875
Cement (50 kg bags)827 bags
Steel (Grade-60 bars)4,489 kg (4.5 tons)
Sand3,072 cft
Crush (aggregate)1,890 cft

Open the full calculator on PakHisaab.com ↗

Quantities per square foot

The defaults come from the published bill of quantities of a real Lahore project. Other published estimates run higher, especially for steel in heavier RCC designs.

MaterialDefault, per sq ftPublished range
Bricks30 bricks20–50 bricks
Cement bags0.35 bags0.35–0.6 bags
Steel1.9 kg1.9–4 kg
Sand1.3 cft1.1–3 cft
Crush0.8 cft0.8–2 cft

Example: 5 Marla double-storey

For 2,250 sq ft covered with 5% wastage you need about 70,875 bricks, 827 bags of cement, 4.5 tons of steel, 3,072 cft of sand and 1,890 cft of crush.

Frequently asked questions

How are the quantities estimated?

Covered area × a quantity per square foot for each material, plus a wastage allowance. The default figures come from a published April 2026 bill of quantities for a 5 marla, ground-plus-one house in Lahore (2,648 sq ft covered).

Why do published estimates differ so much?

Quantities depend on the design: the number of storeys, column and beam sizes, slab thickness, wall thickness and soil. Published Pakistani estimates range from about 1.9 to 4 kg of steel and 20 to 50 bricks per square foot. Change the figures to match your drawings.

Should I order exactly these amounts?

No. Use them for budgeting and comparing quotes. Before ordering, get a bill of quantities from your engineer or contractor based on the approved drawings, and buy in stages as work progresses.

Does this include finishing materials?

No. It covers the grey structure only: bricks, cement, steel, sand and crush. Tiles, paint, wood, plumbing and electrical items are extra. For a total budget, use the construction cost calculator.

Why covered area and not plot size?

Materials depend on how much you build, so count every floor. A 5 marla plot is about 1,125 sq ft, but a double-storey house on it has roughly twice that covered area.

Related calculators

Add this calculator to your website

Free for blogs, forums and business sites. Paste this code where you want the calculator to appear. It stays up to date automatically.

Sources

This calculator gives an estimate for guidance. It is not official advice. Rates and rules change, so confirm important decisions with the relevant authority or a qualified professional. See how we calculate, or report a mistake.