Solar net billing in 2026: how a new consumer applies, what it costs and how long it takes

In short

Step-by-step guide to new rooftop solar under NEPRA’s Prosumer Regulations 2026: eligibility, documents, the DISCO timeline, one-off costs, sizing and payback.

Work it out with the Solar size & payback →

Since 9 February 2026, new rooftop solar goes on net billing under the NEPRA (Prosumer) Regulations 2026. We have already explained the difference from net metering, the buyback rate and the battery question in net metering vs net billing. This guide is about the next step: what to check before you buy panels, which documents you need, how long your distribution company (DISCO) gets for each stage, and when the system pays back once one-off costs are included.

Five rules that decide whether you qualify

RuleWhat it means for you
Only 3-phase 400 V or 11 kV consumersA single-phase home must change its connection first.
System no bigger than your sanctioned loadCheck the sanctioned load on your bill; raise it first if it is too low.
Solar on your transformer capped at 80% of its ratingPast that, the company will not accept new applications; ask your SDO before you buy.
25 kW or less: approved by your DISCO, no feeAbove 25 kW needs NEPRA’s concurrence and Rs 1,000 per kW, for example Rs 30,000 for 30 kW.
250 kW or moreA load flow study by the DISCO or a consultant registered with the Pakistan Engineering Council is required.

Before you buy panels

Documents you need

The standard application form in the regulations (Schedule II) and DISCO checklists ask for:

For a system above 25 kW, the file sent to NEPRA also includes the concurrence application (Schedule III), proof of the fee, and an affidavit on Rs 50 non-judicial stamp paper attested by an oath commissioner (Schedule V).

Where to apply

The regulations require the company to give you its approved forms and information free within two working days of asking.

The timeline, step by step

StepWhoWorking days
Give forms and informationDISCO2
Acknowledge the application and list anything missingDISCO5
Supply missing documentsYou3
Initial review (if not feasible, returned with reasons within 3 days)DISCO15
Sign the agreementBoth7
Connection charge estimate (demand notice)DISCO7
Pay the estimateYou7
Install the meter and connectDISCO15
NEPRA concurrence (only above 25 kW)NEPRA7

So even when everyone meets the deadlines, it takes about 58 working days. Under the agreement you must tell the company in writing that installation is complete at least 15 working days before connecting, and the company has 10 working days to test the system. Net billing starts once the approval or concurrence is granted, and if the system is not running within six months of it, you need a fresh approval.

One-off costs to budget for

There is no official price list for these; take the figures from your company’s demand notice and your installer’s written quote.

How big a system to install

Under net billing, power you export sells cheaply, so a system bigger than you need adds little. From our solar calculator (120 units per kW a month, 60% used at home):

Units a monthSystemCostMonthly savingPayback
3002.5 kWRs 275,000Rs 9,9602.3 years
5004.5 kWRs 495,000Rs 16,9202.4 years
8007 kWRs 770,000Rs 26,8802.4 years

If your sanctioned load is below the suggested size, either install a smaller system or get the load raised first. Remember that a sanctioned load of 5 kW or more moves you to the peak and off-peak tariff, as our earlier guide explains.

Worked example: payback with one-off costs

A home using 500 units a month installs 4.5 kW for Rs 495,000 and saves about Rs 16,920 a month, so it pays back in 2.4 years. Now suppose the meter, connection work and change to three-phase add Rs 60,000 (an example only). Payback becomes (495,000 + 60,000) ÷ (16,920 × 12) = 2.7 years.

We have not found a clear NEPRA notification of the buyback rate, and NEPRA can change it during the agreement. If the buyback were Rs 11 instead of Rs 8, the monthly saving would be Rs 17,640 and payback 2.3 years. The difference is small: most of the saving comes from power you use at home.

After you are connected

Frequently asked questions

How long does a net billing connection take?

If every deadline in the regulations is met, about 58 working days (roughly three months) from asking for the forms to the meter being installed, plus your own time to fix missing documents and pay. Billing for exports starts only after your company’s approval (25 kW or less) or NEPRA’s concurrence (above 25 kW).

Can my solar system be bigger than my sanctioned load?

No. Regulation 3(2) says the system’s capacity cannot exceed the sanctioned load of the premises. If you want a bigger system, apply to your company to raise the sanctioned load first. Older DISCO checklists allowed up to 1.5 times the load, but that was under the repealed 2015 rules.

Who pays for the meter?

You do. The prosumer pays all costs up to the interconnection point, including the metering installation, through the connection charge estimate. If the company has no meter in stock, you may buy one yourself, and the company tests it before installing it.

Can I add panels later?

Only with permission. The agreement asks for at least 40 working days’ notice and a revised application before any change to the system’s maximum output or interconnection equipment, and you must not install the change until it is approved again.

What can I do if my DISCO delays or refuses?

The regulations say approval must not be unreasonably withheld, and set working-day limits for each step. Any dispute between a prosumer and the company goes to NEPRA for decision under regulation 17. Keep copies and dates of everything you submit.

Calculators for this guide

Sources

This guide explains the rules for general information. It is not official, legal or tax advice. Rules change, so check the official source or a qualified professional before acting. See how we check our information.